top of page

Material Requirements Planning

Problem

Time Saved: 

8 hr/wk

A control valve company approached VyTech to enhance their MRP process. Their planners were spending eight hours a week analyzing their current MRP output to determine what they actually needed to produce and when. The ERP system's MRP module provided planned orders to fulfill customer demand but failed to address key issues. It didn’t verify if the parts could be produced with the current inventory, whether using available inventory would compromise other orders, or if partially fulfilling an order was worthwhile. This entire process was highly manual and inefficient.

Solution

VyTech leveraged the company’s existing data infrastructure to develop a streamlined, one-click tool that saved planners eight hours a week. The solution analyzed the ERP’s supply and demand output, reviewed current inventory levels, and incorporated custom planning parameters. It determined how much to build, when to build it, and prioritized production to ensure that no inventory was diverted from existing orders.

bottom of page